Storage lien (UK)
A storage lien is the operator’s right to hold on to a customer’s stored goods when licence fees go unpaid — and, after following the statutory notice procedure, to sell them and take from the proceeds what fell due before the notice, plus the costs of sale. In England and Wales it is normally a contractual right, created by the storage licence agreement and exercised within the limits set by the Torts (Interference with Goods) Act 1977.
By Phil McParlane, Founder
Published 17 October 20263 min read

A storage lien is the self-storage operator's right to hold on to a customer's stored goods as security for unpaid licence fees — and, at the end of a strict statutory process, to sell those goods and take from the proceeds what fell due before the notice, plus the costs of sale. It is the final step in an arrears escalation, sitting well beyond payment reminders, late charges and the suspension of access to the unit (see overlocking).
In England and Wales this right is, for practical purposes, contractual: it exists because the storage licence agreement says it does, and it can be exercised safely only within the limits the law places on disposing of another person's goods.
Where the right comes from
Liens arising automatically at common law are confined to narrow situations — classically where someone has improved goods by working on them. Simply keeping goods safe does not generally create one. That is why storage licence agreements usually contain express clauses doing two jobs:
- a lien — the operator may retain the goods while any sums due under the agreement remain unpaid; and
- a power of sale — after following the statutory procedure, the operator may sell the goods and apply the proceeds to the sums that fell due before the notice and the costs of sale.
Without those express terms, an operator left holding uncollected goods is a bailee with fewer contractual rights, although the Act's sale provisions are not limited to contractual bailments. And because many storage customers are consumers, the clauses themselves must be written plainly and be fair when they are agreed — a lien term is part of a consumer contract, not a blank cheque.
The statutory guard-rails
The contract alone is not enough: the CMA's guidance says terms that allow a sale without adequate notice are unlikely to be fair to a consumer. When an operator moves from retaining goods to disposing of them, the Torts (Interference with Goods) Act 1977 (sections 12–13 and Schedule 1) sets out a route for a bailee in England and Wales to sell uncollected goods.
Where the position is uncertain, section 13 of the Act also lets a bailee ask the court to authorise a sale, and the court's decision is conclusive as against the customer, subject to any right of appeal.
Contractual lien arises The storage licence agreement lets the operator retain the goods while sums due under the agreement remain unpaid, backed by an express power of sale.
Details
Liens rarely arise automatically at common law for simply keeping goods safe — the express clause is what creates the right.Notice of intention to sell Before selling, the operator gives written notice that states its own name and address, identifies the goods and where they are held, gives the amount that became due before the notice, and names the date on or after which it proposes to sell.
Details
A defective notice, or notice to the wrong address, can leave the operator without the entitlement the Act gives.Wait — at least 3 months Where the arrears arose before the notice was given (the normal case), Schedule 1 requires at least three months between the notice and the earliest date of sale.
Details
Selling before the three months have run leaves the sale outside the entitlement the Act gives, and can amount to conversion.Sell — best method reasonably available The accounting is taken on the footing that the operator used the best method of sale reasonably available in the circumstances — not a licence to dump goods at any price.
Account for the surplus The operator keeps only what was owed before the notice plus the costs of sale; any surplus belongs to the customer and must be held for and returned to them.
Details
The operator is liable to account for the surplus, and a defective notice or an early sale can expose it to a claim in conversion for the value of the goods.
Torts (Interference with Goods) Act 1977, ss.12–13 and Schedule 1. England & Wales. General information, not legal advice.
Why the process matters
Getting this wrong is not a paperwork problem. Selling goods without the entitlement the Act gives a bailee who has followed its procedure, for example after a defective notice, a notice to the wrong address or a sale before the three months have run, can be conversion: the operator can be liable to the customer for the value of the goods, which can far exceed the arrears the sale was meant to recover. Keeping the surplus leaves the operator liable to account for it. Disciplined operators therefore treat the lien as a gated, evidenced process rather than a discretion, and good billing and collections software records the arrears and every reminder with its date, so the trail starts early; keep the notice, the sale, the proceeds and the surplus on the same file, so the trail exists if the sale is ever challenged.
Selling uncollected goods properly is a subject in its own right: the statutory route in England and Wales is set out in our guide to abandoned storage units and the Torts Act, which also lists the events that stop the process: a customer's death or insolvency, a dispute about the goods and a breathing space. The lien itself is created by the storage licence agreement, and the access restriction that usually precedes any sale is overlocking.
Phil McParlane, Founder, StoreBay
Phil is the founder of StoreBay, the UK self-storage management platform. He writes about starting, running and growing storage businesses — the operational detail, not the fluff. About StoreBay